SBI Term Loan: RLLR: 8.15 | 7.25% - 8.45%
Canara Bank: RLLR: 8 | 7.15% - 10%
ICICI Bank: RLLR: -- | 8.5% - 9.65%
Punjab & Sind Bank: RLLR: 7.3 | 7.3% - 10.7%
Bank of Baroda: RLLR: 7.9 | 7.2% - 8.95%
Federal Bank: RLLR: -- | 8.75% - 10%
IndusInd Bank: RLLR: -- | 7.5% - 9.75%
Bank of Maharashtra: RLLR: 8.05 | 7.1% - 9.15%
Yes Bank: RLLR: -- | 7.4% - 10.54%
Karur Vysya Bank: RLLR: 8.8 | 8.5% - 10.65%

Gokhale Bridge reopens after seven years, restoring vital east-west link in Mumbai

#Infrastructure News#India#Maharashtra#Mumbai City
Last Updated : 14th May, 2025
Synopsis

After enduring seven years of partial closures, delays, and detours, commuters in Mumbai can now access the fully reopened Gokhale Bridge in Andheri, marking a crucial step in restoring the east-west corridor. The INR 90 crore reconstruction project, which faced repeated setbacks due to coordination challenges between the BMC and Western Railways, has now been completed with two operational lanes in each direction. Civic engineers and local groups have expressed relief at the long-awaited reopening.

The Gokhale Bridge in Andheri, Mumbai, has finally reopened to the public after a prolonged period of partial closures and reconstruction, bringing much-needed respite to commuters who have faced severe traffic congestion and detours since its closure in 2017. With both the west-to-east and east-to-west lanes now fully operational, traffic flow in the area is expected to significantly improve.


Earlier this year, the bridge had been partially reopened with a single arm operational in February. However, the completion of the second arm has now restored full functionality to the critical east-west connector. Civic authorities confirmed that work on utility infrastructure and approach roads was concluded earlier this week, paving the way for the bridge's complete use.

Initially deemed unsafe in 2017 after the collapse of the Elphinstone Bridge, the Gokhale Bridge was subsequently closed, and demolition commenced in 2022. The rebuilding process was marred by delays attributed to coordination issues between the BMC and Western Railway, the latter of which owns sections of land beneath the bridge. Western Railway was tasked with constructing the bridge section over the tracks, while the BMC managed the remaining stretch.

According to civic officials and senior engineers from the bridges department, the project involved the use of 1300 tonnes of steel and was completed at a cost of approximately INR 90 crore. The engineering team navigated complex logistical challenges to complete the structure.

Local civic groups and commuters, who had consistently advocated for timely project completion, have expressed their relief at the bridge's reopening, emphasising its critical role in daily connectivity across Andheri.

Despite the challenges encountered, the completion of the INR 90 crore project signifies a crucial step in enhancing Mumbai's east-west connectivity, particularly for Andheri's commuters. With the bridge now fully operational, the BMC and Western Railways have successfully delivered on a vital infrastructure commitment, alleviating a significant traffic bottleneck in the area.

Have something to say? Post your comment