Dharavi redevelopment project faces hurdles in acquiring temporary housing

Synopsis

The ambitious Dharavi Redevelopment Project, aimed at transforming Asia's largest slum with over 700,000 residents, encounters challenges in acquiring temporary housing for displaced residents during construction. The project, led by Dharavi Redevelopment Project Pvt Ltd (DRPPL) in partnership with Adani Realty, seeks 334 tenements for relocation. Despite acquiring 27.5 acres from railways, securing the remaining land from other agencies is pending, impacting project timelines. Disagreements between DRPPL and MHADA over payment for temporary housing further complicate matters. Resolving these issues is crucial to ensuring smooth relocation and progressing with this transformative urban redevelopment initiative in Mumbai.

10 sec backward button
play pause button
10 sec forward button
0:00
0:00

The ambitious Dharavi Redevelopment Project, aiming to transform Asia's largest slum with over 700,000 residents, faces a new hurdle - acquiring temporary housing for displaced residents during construction.

The Dharavi Redevelopment Project Pvt Ltd (DRPPL), a government body partnered with Adani Realty as the lead developer, has requested 334 tenements to relocate residents. However, securing temporary housing adds to the existing challenges of land acquisition.

The project initially sought 1,255 acres from various government agencies. So far, only the railways have handed over 27.5 acres, with the remaining land acquisition from other agencies still ongoing. This delay in securing the total land area could further impact the project timeline.

DRPPL has approached government agencies like the Slum Rehabilitation Authority (SPPL) and the Maharashtra Housing Area Development Authority (MHADA) for existing buildings in Dharavi that could be used as temporary housing.

However, a disagreement has arisen between DRPPL and MHADA. While MHADA is willing to provide 5 buildings in Sector 5 with a total construction cost of Rs 641 crore, they are seeking full payment including Rs 183 crore in interest. DRPPL agrees to pay the construction cost but contests the interest amount. This dispute is now with the state government for resolution.

The lack of temporary housing creates a significant hurdle for the project. Relocating residents during construction is crucial to avoid disruption and ensure their safety. Delays in acquiring both land and temporary housing could significantly impact the project's overall timeline.

The success of the Dharavi Redevelopment Project hinges on addressing these challenges. Residents have concerns about the relocation process, the quality of temporary housing, and potential delays. Transparency and clear communication from DRPPL are essential to address these anxieties.

The Dharavi Redevelopment Project is a complex undertaking with the potential to improve the lives of thousands of residents. While land acquisition progresses, resolving the issue of temporary housing is a critical next step. Open communication with residents and a collaborative approach with government agencies will be key to overcoming these hurdles and ensuring the project's success.