The reconstruction of Mumbai's Gokhale Bridge has faced a setback as the BMC's bridges department seeks the demolition of 13 structures on the Andheri East side to accommodate a crane necessary for assembling the bridge girder. While the structures hinder construction, concerns arise due to monsoon-related court orders preventing demolitions and evictions. The contractor requires more space to manoeuvre the crane, but only nine encroached structures can be demolished in October post-monsoon. The bridge, previously marred by delays, must meet a deadline for one side's completion by October. The project reflects challenges in urban infrastructure development amidst regulatory constraints.
The reconstruction of Mumbai's Gokhale Bridge, a vital connector between Andheri's east and west regions, has encountered another hurdle. The bridges department of the Brihanmumbai Municipal Corporation (BMC) has called for the demolition of 13 structures on the Andheri east side to facilitate the movement of a crane essential for assembling the bridge's girder. This latest development underscores the challenges faced in the ambitious project's execution.
Officials from the BMC have communicated their need for the K east ward to clear these structures to create sufficient space for the crane's manoeuvrability. However, the endeavour faces complications due to monsoon-related court orders, which prohibit demolitions and evictions during the monsoon season. The complexity arises from the necessity of the demolition to progress with the construction while adhering to the legal constraints.
Initially, the bridges department had sought 10 meters of clearance from the ward, which was achieved. Unfortunately, the crane's operational requirements necessitate additional space, forcing a more extensive demolition of partially removed structures. Out of the 13 structures, four hold legal status and will need complete displacement under the Project Affected People (PAP) framework. The procedure for these four structures will commence soon. Meanwhile, the remaining nine structures face encroachment issues and can only be demolished in October, following the monsoon season.
This predicament has created urgency, as one side of the bridge must be completed by October to meet project deadlines. P. Velrasu, Additional Commissioner (Projects) of the BMC, visited the site with senior officials from the bridges department and the ward to assess the progress. Despite challenges, Velrasu expressed satisfaction with the coordinated efforts of multiple agencies involved in the project.
The delay in the Gokhale Bridge reconstruction project has previously garnered attention, with the Comptroller and Auditor General (CAG) report indicating a four-year delay. The report highlighted that the BMC did not initiate timely reconstruction despite a part of the bridge collapsing in July 2018 and recommendations from the structural auditor. Instead, Western Railways, in collaboration with the BMC, conducted substantial repair work from October 2018 to February 2020, using funds from the BMC. The reconstruction began much later, with the railway portion demolition in November 2022 and the bridge's complete closure in the same month.
The Gokhale Bridge's significance lies in being a crucial route in Andheri, experiencing high traffic. Following its partial collapse in 2018 resulting in fatalities, the bridge remained partially open as the BMC embarked on a phased rebuilding approach. However, the current impasse illustrates the intricate balance between project advancement and legal constraints, a common challenge in urban infrastructure development.
Moreover, this scenario highlights broader urban planning challenges. The need to balance development, safety, and regulatory adherence underscores the complexities faced by municipalities in executing infrastructure projects. Projects often involve a multitude of stakeholders, including government bodies, regulatory authorities, contractors, and affected communities.
Additionally, the mention of the delayed Carnac Bundar bridge reconstruction due to unauthorized structures further exemplifies the recurrent challenges that arise in infrastructure projects within urban settings. The unavailability of land and the presence of unauthorized structures can significantly impact project timelines, highlighting the need for comprehensive urban planning strategies.
In conclusion, the roadblock encountered during the reconstruction of Gokhale Bridge emphasizes the intricacies involved in executing urban infrastructure projects. The delicate balance between construction progress, regulatory compliance, and community concerns underscores the challenges faced by municipal authorities. The BMC's efforts to resolve the current dilemma and adhere to project timelines reflect the dedication required to transform urban infrastructure while navigating legal and logistical complexities.